Case Studies - Education - Adult

The following Modular Adult Education Center case studies highlight some modular building projects we are proud to present. Each project had a particular challenge Modular Genius was faced with. The challenge the customer presented was either speed, time or quality. Modular Genius solved each challege with a solution to meet the customers expectations.

Please contact us if you want to discuss your specific project further 888-420-1113.

View the case studies below by clicking on the PDF or thumbnail icon.

Case Studies - Modular Adult Education Centers

File Description View
PDF

Cecil CC - Adult Classroom / Training Center

[CHALLENGE]
A Technical College had to relocate their existing truck driver training offices and classrooms. The space which they were using was old and out dated. They needed to move out and be up and operational in a short period of time for seamless transition.

[SOLUTION]
Modular Genius installed a 1,920 sq ft classroom and office space for their new facility. The turnkey services provided by Modular Genius included installation of fresh water and sewer tanks, decks and canopies as well as leveling the pad for the modular buildings. The fabrication and installation was complete in 60 days from award.

preview
PDF

Delmarva - Adult Training Center

[CHALLENGE]
A power company had to relocate their existing power pole training offices and classrooms. The space which they were using was old and out dated. They needed to move out and be up in operational in a short period of time for seamless transition.

[SOLUTION]
Modular Genius installed 1,728 sq ft of classroom and office space for their new facility. The additional services provided by Modular Genius included demo of the existing modulars, installation of prefabricated aluminum decks, ramps and canopies, skirting and accordion partition walls to divide the classrooms inside the modular building. The fabrication and installation was complete in 60 days for award.

preview
PDF

PEPCO - Modular Training Center

[CHALLENGE]
A power company had to relocate their existing power pole training offices and classrooms. They needed to move out and be up and operational in a short period of time for a seamless transition.

[SOLUTION]
Modular Genius installed a 2,880 sq ft modular training center for their new facility. The fabrication and installation was complete in 60 days from award, inclusive of prefabricated aluminum decks and ramps and accordion walls inside the training rooms.

preview
PDF

SJDB - Modular Classrooms

[CHALLENGE]
A regional religious institution was in need of additional classroom space for adult education. They had a small corner of the parking lot which they could build on, and needed it completed over the summer months in order to be in use by the start of the school year.

[SOLUTION]
Modular Genius built a H Shaped modular classroom building approx. 1,500 sq ft. The portable classroom building was installed with site built wood steps and ramps. The exterior was an esthetic compliment to the campus choosing colors to match an existing building. The construction of the modular building and installation was complete in 90 days from award to occupancy. 