Colgate Elementary School
[CHALLENGE] Due to the constant change in demographics in Baltimore County
Maryland and, the county was required to add a classroom at Colgate Elementary
School in Baltimore Maryland.
[SOLUTION]
Modular Genius has a 3 year contract to provide modular classroom buildings
for sale or lease for the Baltimore County Cooperative. The Cooperative
consists of participating surrounding counties in the State of Maryland.
Upon notification, Modular Genius built and installed the modular classroom
for the upcoming school year.
|
|
|
Deer Park Middle Magnet School
[CHALLENGE] In order to efficiently complete the renovation required for Deer Park Middle Magnet School, large sections of the building needed to be closed while construction took place. Baltimore County needed ten classrooms to accomodate the displaced students during the phased project.
[SOLUTION]
Modular Genius provided a 10,000 square foot modular classroom complex with 10 classrooms and a bathroom module for the duration of the renovation. The complex included lockers, shelving, markerboards, and tack boards. The building was installed in a two-week period.
|
|
|
Delaware State University - Business and Fitness Center
[CHALLENGE]
Delaware State University had to relocate their 5,000 square foot Fitness Center to make room for the construction of a new building. Relocation had to take place immediately following school commencement and be completed prior to school starting.
[SOLUTION]
Modular Genius dismantled and moved the 5,000 square foot facility including free weights, treadmills, and other fitness equipment to an off-site storage facility. The modular building was dismantled and relocated across campus and then installed. All of the equipment was moved back into the facility. The project was a complete turnkey inclusive of utility connection.
|
|
|
Beechfield Elementary School
[CHALLENGE] A public elementary school was in need of additional classrooms due to redistricting.
[SOLUTION]
Modular Genius design built a 10,780 square foot facility inclusive of multiple classrooms. The building was installed inclusive of site civil engineering, permitting, and complete utility connection during the summer and ready for occupancy prior to the start of school.
|
|
|
North Bend Elementary School
[CHALLENGE]
A public elementary school was in need of additional classrooms due to redistricting.
[SOLUTION]
Modular Genius, Inc. design built a 5,760 square foot facility inclusive of multiple classrooms. The building was installed inclusive of site civil engineering, permitting and complete utility connection during the summer and ready for occupancy prior to the start of school.
|
|
|
Thurgood Marshall High School
[CHALLENGE]
Baltimore City Public Schools needed to convert an existing elementary school to a high school. The project required adding a 2,160 square foot locker room facility for the varsity athletics. The building had to be delivered and installed during the summer.
[SOLUTION]
Modular Genius, Inc. delivered and installed the 2,160 square foot facility in 45 days. Work consisted of permits, engineering, electric, plumbing, foundation and entrance means. The project was delivered on time and within budget.
|
|
|
Elkton Christian Academy - Elkton, MD
[CHALLENGE] Elkton Christian Academy needed to renovate the school and was in need of classrooms, office space and restrooms. The buildings had to be installed over the summer prior to the start of school.
[SOLUTION] Modular Genius provided 7,400 square feel of buildings. The project was completed in 60 days.
|
|
|
Queen Anne's County Public Schools - Lease
[CHALLENGE]
Queen Anne's County Public Schools wa faced with a need for additional classroom space at various schools.
[SOLUTION]
Modular Genius provided 7 portable classrooms totaling 6,000 square feet. The project was completed in 30 days.
|
|