The following Modular Scale House Weight Station case studies highlight some modular building projects we are proud to present. Each project had a particular challenge Modular Genius was faced with. The challenge the customer presented was either speed, time or quality. Modular Genius solved each challege with a solution to meet the customers expectations.

Please contact us if you want to discuss your specific project further 888-420-1113.

View the case studies below by clicking on the PDF or thumbnail icon.

Case Studies: Modular Scale House Weight Station

File Description View
PDF

SHA MD - Delmar Weigh Station

[CHALLENGE]
The Maryland State Highway Administration needed to replace the weigh station in Delmar, MD. The buildings had to be custom built to meet the specific need of a scale house.

[SOLUTION]
Modular Genius provided a 1,056 square foot building. The project was completed in 90 days.

preview
PDF

SHA MD Warwick - Scale House Weight Station

[CHALLENGE]
The Maryland State Highway Administration needed to replace the weigh station. The buildings had to be custom built to meet the specific need of a scale house.

[SOLUTION]
Modular Genius provided a 1,200 square foot building. The project was completed in 90 days.

preview
PDF

SHA College Park - Modular Scale House

[CHALLENGE]
A State Highway was in need of replacing a dilapidated scale house. The decision to construct a modular building was made to insure the replacement would happen fast with little down time for the scale.

[SOLUTION]
Modular Genius remove the old office trailer off site and replaced it with a 1,440 sq ft new modular building. The turnkey modular building project was completed in 90 days from notice to proceed. The scale house was only down for 30 days.

preview
PDF

SHA MD Parkton - Modular Scale House

[CHALLENGE]
A State Highway was in need of replacing a dilapidated scale house. The decision to construct a modular building was made to insure the replacement would happen fast with little down time for the scale.

[SOLUTION]
Modular Genius remove the old office trailer off site and replaced it with a 1,440 sq ft new modular building. The turnkey modular building project was completed in 90 days from notice to proceed. The scale house was only down for 30 days.

preview
PDF

OC - Prefabricated Truck Scale House

[CHALLENGE]
An industrial company was in need of a scale house to check trucks in and out of a new entrance. The decision to construct a modular building was made to insure a speedy installation.

[SOLUTION]
Modular Genius had a 240 sq ft new modular building constructed for the customer. The prefabricated building was delivered and installed in 90 days from notice to proceed.